01 · BMS & Building Controls

BMS Alarm Management: Making Alarms Useful Again

  • By Flair Facilities Ltd engineering team
  • Published
  • Updated
  • Read 6 min
Quick answer

Good BMS alarm management means every alarm is real, has a clear priority, reaches the right person and has a defined response. Most buildings suffer from alarm floods, where nuisance and duplicate alarms bury genuinely important events. The fix is a structured alarm review: classify alarms by consequence, remove or delay nuisance alarms, suppress consequential alarms, and route critical ones to people who can act on them.

Why do BMS alarms stop being useful?

Alarms accumulate. Each commissioning engineer, contractor and building change adds a few. Limits are set too tight, sensors drift, plant is decommissioned but its alarms remain. Eventually operators see hundreds of alarms a week, learn to acknowledge them without reading, and the one that matters, such as a boiler lockout on a cold Friday evening, is missed.

Common symptoms of poor alarm management

  • Alarm lists that are never empty
  • The same alarms recurring daily and being acknowledged without action
  • Alarms for plant that no longer exists
  • No distinction between a filter alarm and a gas valve alarm
  • Critical faults discovered by occupants before the BMS
  • No record of who responded to an alarm or what they did

What causes alarm overload?

CauseExampleRemedy
Limits too tightRoom high-temperature alarm at 23°CSet limits on consequence, add delays
No time delayPressure blip during pump changeover raises alarmAdd a delay appropriate to the risk
Consequential alarmsOne chiller failure triggers twenty temperature alarmsSuppress dependants while root alarm is active
Failed sensorsFaulty sensor alarms continuouslyRepair or replace the sensor
Stale configurationAlarms on decommissioned plantRemove after verification
Out-of-hours alarmsComfort alarms when the building is emptyEnable only during occupancy

How to structure alarm priorities

Classify alarms by the consequence of not responding, not by the equipment type.

PriorityConsequenceExampleTarget response
CriticalSafety risk or loss of critical serviceGas valve closed, total heating loss in healthcare, plant room floodImmediate, 24/7
HighSignificant impact if not addressed within hoursBoiler lockout with standby running, chiller faultSame day
MediumDegraded performanceFilter dirty, zone out of rangeNext working day
LowMaintenance informationRun-hours threshold, minor deviationsScheduled

Running an alarm review

  1. Export alarm history for the past one to three months.
  2. Rank by frequency. The top twenty alarms typically make up most of the volume.
  3. Investigate each frequent alarm: is it a real fault, a bad limit, a failed sensor or redundant?
  4. Agree priorities with the building team and maintenance contractor.
  5. Implement changes through a competent controls engineer, documenting each one.
  6. Define response actions for each critical and high alarm.
  7. Review monthly for the first quarter, then quarterly.

Safety: Never remove or delay alarms from safety-related functions such as gas detection, fire interlocks, frost protection, high-limit thermostats or plant room flooding without a documented risk assessment and the agreement of the responsible person. Alarm changes should be made by a competent controls engineer and recorded.

When should you involve a controls engineer?

For any changes to alarm limits, delays, suppression logic or routing; when the head-end software or outstations need updating; and when alarm notification such as email, SMS or remote monitoring needs setting up or testing.

Practical recommendations for facilities managers

  • Keep an alarm register listing each alarm, priority, limit, delay and response
  • Target an alarm list that operators can realistically clear each day
  • Ensure critical alarms reach a person who can act out of hours
  • Test alarm routes, such as forcing a test alarm, at least annually
  • Review repeating alarms in monthly maintenance meetings
  • Link alarm history to planned maintenance so recurring faults become PPM actions

See also BMS temperature sensor faults and the BMS and Building Controls guide.

flairfacilities.co.uk

More BMS expertise from Flair Facilities

Frequently asked questions

What is an alarm flood?

An alarm flood is when more alarms arrive than an operator can reasonably assess, often hundreds in a short period. It typically happens when one failure triggers many consequential alarms or when nuisance alarms have accumulated over time.

What is a consequential alarm?

An alarm that results from another fault. For example, when a boiler fails, the low flow temperature, zone temperature and other alarms that follow are consequential. Suppressing them while the root alarm is active helps operators focus.

Should we just switch off nuisance alarms?

Not without investigating. A nuisance alarm may be caused by a real underlying fault, a poor setting or a failing sensor. Fix the cause, adjust the limit or add a time delay, and document the change.

Who should receive critical BMS alarms out of hours?

Whoever can act on them, typically a security control room, on-call engineer or maintenance contractor helpdesk, with an agreed escalation path. Test the route periodically to make sure it still works.

UK technical references

Primary sources and industry guidance relevant to this topic. Always check you are working to the current edition.

  1. CIBSE Guide H: Building control systems (via the CIBSE knowledge portal) — Chartered Institution of Building Services Engineers
  2. Building Controls Industry Association — BCIA
  3. Managing for health and safety — Health and Safety Executive

This guide is general technical information for commercial property teams in the UK. It does not replace a site-specific assessment. Gas work must be carried out by a Gas Safe registered engineer, and work on electrical, pressurised or combustion equipment by competent, appropriately qualified people.

BMS London at a glance