09 · Planned Maintenance

Commercial Mechanical PPM Checklist

  • By Flair Facilities Ltd engineering team
  • Published
  • Updated
  • Read 8 min
Quick answer

A mechanical PPM checklist should list every maintainable asset, the tasks it needs, how often, who is competent to do them and what evidence must be recorded. Typical assets include boilers, pumps, pressurisation units, calorifiers, booster sets, AHUs, fan coils, chillers, BMS and water treatment. Statutory tasks such as gas safety, F-gas leak checks and pressure system examinations must be scheduled at their required intervals; other frequencies should follow industry task libraries such as SFG20 and the asset's criticality.

How to use this checklist

Treat this as a framework to check your existing PPM schedule against, not a replacement for a site-specific programme. Frequencies shown are typical; your actual schedule should reflect statutory requirements, manufacturer instructions, insurer conditions, a recognised task library and how critical each asset is.

Key: S = statutory, M = mandatory (manufacturer or insurer), O = optimal good practice.

Heating and hot water

AssetTypical frequencyKey tasksType
Gas-fired boilersAnnually (min.)Service, combustion analysis, safety device checks, flue inspectionS / M
Gas installationAnnuallySafety inspection, tightness test where requiredS
Boiler sequence controllerAnnuallyCheck lead/lag rotation, setpoints, enable signalsO
Circulation pumps6–12 monthsNoise, vibration, seals, changeover test, motor currentO
Pressurisation unitAnnuallySettings, pump operation, break tank, alarmsO
Expansion vesselsAnnuallyPre-charge check, membrane conditionO
CalorifiersMonthly / annuallyTemperature monitoring, blowdown, relief valve checks, inspectionS (L8) / O
Water treatment (closed systems)QuarterlySampling, inhibitor levels, dosingO

HVAC and ventilation

AssetTypical frequencyKey tasksType
AHUsQuarterly to annuallyFilters, belts, fans, dampers, coils, drains, heat recoveryO
Fan coil unitsAnnuallyFilters, condensate drains, fans, valves, controlsO
ChillersQuarterly to biannuallyPerformance, refrigerant checks, oil, controlsM / O
Refrigerant systemsPer F-gas chargeLeak checks and recordsS
Air conditioning systems over 12 kWEvery 5 yearsEnergy assessment (TM44)S
Kitchen extractPer risk and insurerDuctwork cleaning, fans, filtersM
Toilet and general extractAnnuallyFan operation, airflow, controlsO

Water services

AssetTypical frequencyKey tasksType
Booster setsAnnuallySet pressure, vessel pre-charge, changeover, controllerO
Cold water storage and break tanksPer risk assessmentInspection, temperature, cleaning where neededS (L8)
OutletsPer water safety planTemperature checks, flushing of little-used outletsS (L8)
Thermostatic mixing valvesPer risk assessmentTemperature verification, servicingO

Controls and BMS

AssetTypical frequencyKey tasksType
BMS supervisor and outstationsAnnuallyBack-ups, software health, communication checksO
Critical sensorsAnnuallyCalibration of outside air, supply and flow sensorsO
AlarmsQuarterlyReview priorities, test critical alarm routingO
Schedules and setpointsQuarterlyCompare against occupancyO

Pressure systems

AssetTypical frequencyKey tasksType
Equipment in PSSR scopePer written schemeExamination by competent personS
Relief and safety valvesPer written scheme or annuallyInspection and testingS / O

Safety: This checklist describes engineering tasks for competent people. Gas, electrical, pressurised, refrigerant and rotating plant work must be carried out by appropriately qualified and registered engineers using safe isolation and permit-to-work procedures where required.

What should each PPM record contain?

  • Asset reference and location
  • Task carried out and date
  • Readings: pressures, temperatures, currents, combustion figures
  • Observations and photographs
  • Defects found, with priority
  • Engineer name and competence reference
  • Next due date

Practical recommendations for facilities managers

  • Reconcile the PPM schedule with an up-to-date asset register
  • Mark every statutory task and track its due date separately
  • Ask for readings, not just completion ticks
  • Review PPM completion and open defects monthly
  • Schedule heating PPM before winter and cooling PPM before summer
  • Review frequencies annually using breakdown history and asset condition

For the planning process behind this checklist, see Planned Preventative Maintenance. For specific equipment, see circulation pump failure and pressurisation unit faults.

flairfacilities.co.uk

More BMS expertise from Flair Facilities

Frequently asked questions

What does PPM stand for?

Planned preventative maintenance: scheduled inspection, servicing and testing designed to prevent failures and maintain compliance, as opposed to reactive repairs after something breaks.

Are the frequencies in this checklist mandatory?

No. They are typical starting points. Statutory frequencies are set by law or the competent person, mandatory frequencies by manufacturers or insurers, and others should be set using a recognised task library and a risk-based review of your assets.

Who should carry out mechanical PPM tasks?

Competent, appropriately qualified people. Gas tasks need Gas Safe registered engineers with the right categories, refrigerant work needs F-gas certified technicians, and electrical and controls tasks need qualified electricians or controls engineers.

How should PPM results be recorded?

Against each asset, with readings, observations, defects and photographs where useful, rather than a simple tick. Recorded readings let you spot trends such as rising pump vibration or falling vessel pressures.

UK technical references

Primary sources and industry guidance relevant to this topic. Always check you are working to the current edition.

  1. SFG20 maintenance standard — BESA / SFG20
  2. CIBSE Guide M: Maintenance engineering and management (via the CIBSE knowledge portal) — Chartered Institution of Building Services Engineers
  3. Gas Safety (Installation and Use) Regulations 1998 — legislation.gov.uk
  4. F gas in refrigeration, air conditioning and fire protection systems — GOV.UK
  5. Pressure systems guidance — Health and Safety Executive
  6. Legionnaires' disease: ACoP L8 and HSG274 — Health and Safety Executive

This guide is general technical information for commercial property teams in the UK. It does not replace a site-specific assessment. Gas work must be carried out by a Gas Safe registered engineer, and work on electrical, pressurised or combustion equipment by competent, appropriately qualified people.